Offshore References
CAT link refurbishment on BorWin beta
New structural connection for a long-term secure platform link
Service
Structural remediation
Location
BorWin beta offshore platform · North Sea
Result
Completed one week ahead of schedule
A damaged connection between the topside and the cable access tower increased the risk of failure. mh² replaced the critical CAT link with a new, permanent connection – while the platform remained in operation.
The challenge
An unplanned height difference between the connection points created additional loads on the existing CAT connection between the topside and the cable access tower. Rod ends and double joints were overstressed under extreme loads; deformations that had already occurred could have led to further loads and reduced fatigue strength. The connection needed to be replaced promptly.
The remediation had to be carried out on an operational platform. Access, load bearing, and component handling were spatially restricted – at the same time, the replacement had to ensure no uncontrolled load conditions were created on the existing structure.
Our solution
01 · Planning the remediation
Method statements, personnel and offshore workflow planning, as well as quality and inspection documentation structured the project. The remediation solution provided for the new connection to be placed at a lower, permanently load-bearing position.
02 · Manufacturing the new connection
Two new horizontal rod elements with articulated end connections were manufactured, tested, and prepared for offshore transport.
03 · Setting up the work area
Scaffolding, lifting points, chain hoists, and material transport were arranged to allow for the controlled movement of old and new components within the confined space.
04 · Replacing the old structure
The damaged connection was secured and dismantled. Subsequently, the new CAT link was lifted into place, positioned, aligned, and welded.
05 · Inspection and long-term protection
Surveying, welding supervision, and non-destructive testing confirmed the quality of the execution. The coating restored corrosion protection for the demanding offshore climate.
What made this project special
- Work on a structurally critical connection during ongoing platform operations – with load paths controlled at all times.
- Welding, scaffolding, surveying, coating, and NDT services in a single workflow.
- New connection for the targeted 30-year service life.
- Acceleration measures during execution.
The result
The new CAT link was installed, tested, and coated. According to the project review, work began on August 13, 2018, and was completed on October 22, 2018 – one week ahead of the original schedule.
No technical deviations were documented regarding tools, materials, qualifications, or the work steps performed.
Project details
Client
TenneT
Project no.
mh-0268
Period
August–October 2018
Duration
approx. 10 weeks
Scope
1 CAT link · 2 new rod elements
Role
general contractor
Service area
Conversion, Modifications & Repairs
Location
BorWin beta offshore platform · North Sea
Project photos
Insights into execution.







Planning a similar project?
Tell us about your situation — we’ll let you know how we would approach it and what a realistic timeline looks like.