Offshore References
Switchgear replacement at 60 offshore wind turbines in Baltic 2
Series replacement of Flusarc switchgear components under offshore conditions
Service
Switchgear replacement campaign
Location
Baltic 2 Offshore Wind Farm · Baltic Sea
Result
60 turbines processed and documented
60 wind turbines, two different platform types, and complex component transport: for Baltic 2, mh² organized the series replacement of gas tanks in Flusarc medium-voltage switchgear, managing the entire process from work preparation to final electrical testing.
The challenge
The gas tanks of the Flusarc medium-voltage switchgear had to be replaced at 60 offshore wind turbines spread across the site. Each heavy and sensitive component had to be transported from a confined turbine room, across multiple levels and designated lifting points, down to the crew transfer vessel.
Differences between monopile and jacket locations, temporary emergency power supply, mechanical and electrical interfaces, and weather-dependent access all had to be integrated into a repeatable campaign workflow.
Our solution
01 · Standardizing the series process
Method statements, risk assessments, and shared checklists defined a reproducible workflow for preparation, dismantling, transport, installation, and testing.
02 · Safely preparing the turbine
Before each replacement, the initial state and transport route were documented photographically, the switchgear was taken out of service, and a temporary emergency power supply was set up.
03 · Removing the old gas tank
Mechanical and electrical connections were disconnected. Chain hoists, transport dollies, and the turbine's own cranes enabled controlled transport to the external platform and the crew transfer vessel.
04 · Installing the replacement gas tank
The new gas tank was brought in along the reverse transport route, aligned, and integrated mechanically and electrically into the medium-voltage switchgear.
05 · Verifying quality for each turbine
Daily reports, digital photo documentation, before-and-after images, and electrical measurement logs provided comprehensive, turbine-specific final verification.
What made this project special
- Series campaign across 60 turbines at the Baltic 2 offshore wind farm.
- Diverse lifting and transport concepts for monopile and jacket locations.
- Heavy components, confined turbine spaces, and multiple transfer points between chain hoists, dollies, the platform crane, and the crew transfer vessel.
- Integration of mechanical dismantling and assembly, electrical work, logistics, HSE, and documentation.
The result
The project documentation records the gas tank replacement at 60 wind turbines. Individual work and photo documentation files were created for each turbine ID; the campaign ran from June to September 2021.
The standardized process enabled the repeated dismantling, transport, and installation of gas tanks at both monopile and jacket locations. Electrical measurements and turbine-specific condition assessments formed the documented conclusion.
Project details
Client
GE / EnBW
Project no.
mh-0583
Period
June–September 2021
Duration
4 months
Scope
60 turbines
Role
general contractor
Service area
Conversion, Modifications & Repairs
Location
Baltic 2 Offshore Wind Farm · Baltic Sea
Project photos
Insights into execution.








Planning a similar project?
Tell us about your situation — we’ll let you know how we would approach it and what a realistic timeline looks like.